Dear all
programme for Thursday & Friday in week 49/Saacke 6022 & 6020:
Søren comes to UK, and helps MSI to switch ball camps at X Y axis from Saacke & 6022, and replacement of ball camps on the X axis from Saacke 6020.
Problems with the razor in Coolantplant
at the weekend in week 49, we must have emptied kølesmørremiddels tub, and we must have found the reason for, why our scraper doesn't work in coach.
Sam travels back to NZ again Monday afternoon d. 09.10.13.
Visit of KDM & JBY:
Sunday night in week 49 arrives KDM (building responsible in DK) and JBY.
Program for Monday 09.12.13 with Jørgen & Kristian is:
review of our building,
CTS/BMS system, Various problems in the production of machinery,
Air compressor installation in Fradley/meeting with AQ Central Ltd.
programme for Tuesday d. 10.12.13
Status meeting on CTS/BMS system with MSM, WDA, JBY, KDM, MSI & JOK.
Production meeting in Conf room 3: 00. 12.30-13.30/summoned by JBY.
Miscellaneous.
Jørgen & Kristian travels back to the UK on Tuesday afternoon. d. 10.12.13